Workers are repairing the Yuren Street.
Workers are repairing the Yuren Street.
The Yuren Street in Haigang District, Qinhuangdao City was under renovation in the past few days.
Workers from Haigang District Administration demolished the old roadbed with hammer machine and excavator, clearing the construction waste with trucks, reduced dust with water sprayers, and covered the bare land with green net.
The Engineering Management Office of Haigang District Administration focused on improving the traffic of streets and lanes, the road functions, and the flood prevention during the flood season, launching the road renovation, improving the urban road traffic, optimizing the urban road microcirculation system, beatifying road environment, and satisfying people’s travel need.
Since the beginning of April, the renovation of the Yuren Street, the north section of old Qinshan Road, the southwest corner of Yanshan Street and Minzu Road, east ramp of Hongqi Road , Hai’an Road, Xingfuli Street, Hongqiaoli Road, Gangyi Road, and north ramp of Hebei Street Tunnel have been conducted, to breakthrough the “capillaries” of urban roads.
The Engineering Management Office of Haigang District Administration investigated the old streets and roads, and made specific plans to fix the roadbed, rebuild the sidewalks and drainage, dredge the underground pipes, replaced 500 mm diameter drainage pipes, and repair the chain blocks, pavements, kerb, and tree pools. They demolished the concrete roads and renewed them with asphalt. The roads environment and travel conditions have been improved.
The height of the longitudinal slope of the north side of old Qinshan Road was reduced. Asphalt parking lot was built on the east side of Hai’an Roads.
Given that the actual travel conditions of nearby residents, they optimized the construction plan, strengthening the road structure by layering and compacting the subgrade filling, and paved hot asphalt with mechanized construction, to ensure the quality of the project. They paid attention to the dust control, reducing dust by water sprayers and covering the bare land with green net, trying not to influence people’s travelling.
The renovation involves a total road length of more than 3,600 meters. More than 18,000 square meters of asphalt roads were built or rebuilt, more than 16,000 square meters of sidewalks were built or fixed, more than 4,500 meters of kerb was built or repaired, 140 tree pools were built, more than 1,700 meters of rainwater pipelines were laid, 58 rainwater collection ports were built, more than 310 collection ports and inspection wells were repaired, and 450 square meters of asphalt parking lot was built.
At present, the Yuren Street, the north section of old Laoqinshan Road, Hongqiaoli Road, Yanshan Street and the southwest corner of Minzu Road have been under construction, the old roadbeds are demolished, earthwork are transported, and other renovation projects are underway as planned.